Question
Quantitative Aptitude Question on Time and Work
X, Y, Z and W can do a certain piece of work in 10, 15, 25 and 30 days respectively. All of them started the work together but X left the job 2 days before the completion of work, Z left the work 1 day before completion of work, W worked with double of his efficiency. Find total time taken by them to complete the work is how much more or less than the total time taken by X alone to complete the work.
41223 days
41224 days
41225 days
41226 days
41224 days
Solution
The correct option is (B): 41224 days.
Let total work be (LCM of 10,15,25 and 30) = 150
Efficiency of X = (10150) = 15
Efficiency of Y = (15150) = 10
Efficiency of Z = (25150) = 6
Efficiency of W = (30150) = 5
Let work get completed in z days.
[15*(z-2) +6*(z-1) +10z + 52*z] = 150
15z - 30 + 6z - 6 + 10z + 10z = 150
41z - 36 = 150
41z = 186
z =41186
Required difference = 10 - 41186 = 41224 days.