Question
Construction Materials and Management Question on PERT
Which one of the following related to determination of critical path in PERT
A
Event oriented slack
B
Activity oriented slack
C
Event oriented float
D
Activity oriented float
Answer
Event oriented slack
Explanation
Solution
The correct option is(A): Event oriented slack