Construction Materials and Management Question on PERT

Which one of the following related to determination of critical path in PERT

A

Event oriented slack

B

Activity oriented slack

C

Event oriented float

D

Activity oriented float

Answer

Event oriented slack

Explanation

Solution

The correct option is(A): Event oriented slack