Which one of the following divisions is not part of aggregate production planning?
A
Amount of labour to be committed
B
Rate of production
C
Inventory to be carried forward
D
Scheduling of machines.
Answer
Scheduling of machines.
Explanation
Solution
The correct option is (D): Scheduling of machines.