Question
Mathematics Question on Time and Work
Two coal loading machines, each working 12 h per day for 8 days, handle 9000 tonne of coal with an 1 efficiency of 90%, while 3 other coal loading machines at an efficiency of 80% are set to handle 12000 tonne of coal in 6 days. How many hours per day should each machine work?
A
18 h per day
B
16 h per day
C
20 h per day
D
14 h per day
Answer
16 h per day
Explanation
Solution
According to the question,
time amountofworkdone1time1=amountofworkdone2time2
(12×8×.9):(29000)::(6x×.8):(312000)
So, on solving , we get
x =day16hr...
So the correct option is (B)