Question
Architecture and Planning Question on Mathematical Logic
There is a critical activity is going to have a cost of Rs. 30,000. If this activity is getting completed in 15 days and this work will done in 12 days there will be a cost of Rs. 54,000? Statement I: This crashing is advisable economical if indirect cost is Rs. 8,500 per day. Statement II: This crashing is advisable economical if indirect cost is Rs. 10,000 per day.
A
Statement I & II both are correct
B
Statement I & II both are incorrect
C
Statement I is correct & Statement II is incorrect
D
Statement I is incorrect & Statement II is correct
Answer
Statement I is correct & Statement II is incorrect
Explanation
Solution
The correct option is (C): Statement I is correct & Statement II is incorrect