There is a critical activity is going to have a cost of Rs. 30,000. If this activity is getting completed in 15 days and this work will done in 12 days there will be a cost of Rs. 54,000? Statement I: This crashing is advisable economical if indirect cost is Rs. 8,500 per day. Statement II: This crashing is advisable economical if indirect cost is Rs. 10,000 per day.

A

Statement I & II both are correct

B

Statement I & II both are incorrect

C

Statement I is correct & Statement II is incorrect

D

Statement I is incorrect & Statement II is correct

Answer

Statement I is correct & Statement II is incorrect

Explanation

Solution

The correct option is (C): Statement I is correct & Statement II is incorrect