The table shows the activities and their durations and dependencies in a project.Activity | Duration (Days) | Depends on |
---|---|---|
A | 8 | - |
B | 4 | A |
C | 4 | B |
D | 4 | C, L |
F | 4 | A |
G | 4 | F |
H | 6 | G, L |
K | 10 | A |
L | 6 | F, K |
The total duration (in days) of the project is ______ (in integer). |
Answer
The correct answer is 30.