| The table shows the activities and their durations and dependencies in a project.Activity | Duration (Days) | Depends on |
|---|---|---|
| A | 8 | - |
| B | 4 | A |
| C | 4 | B |
| D | 4 | C, L |
| F | 4 | A |
| G | 4 | F |
| H | 6 | G, L |
| K | 10 | A |
| L | 6 | F, K |
| The total duration (in days) of the project is ______ (in integer). |
Answer
The correct answer is 30.