Structural Engineering Question on Construction Management

The table shows the activities and their durations and dependencies in a project.ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K
The total duration (in days) of the project is ______ (in integer).
Answer

The correct answer is 30.