Question

Geomechanics and Ground Control Question on Roof supporting systems

The roof convergence data for 30 days at a monitoring station in a coal mine gallery is given. DayConvergence reading (mm)
00
54.7
1011.3
1619.6
2228.8
3034.8
The management decides on a Trigger Action Response Plan (TARP) if the following two premises occur simultaneously.
Premise 1: Rate of convergence exceeds 1.5 mm/day between two consecutive measurements.
Premise 2: Rate of cumulative increase in convergence exceeds 1.0 mm/day.
Identify the day on which TARP is enforced in that gallery.
A

10

B

16

C

22

D

30

Answer

22

Explanation

Solution

The correct option is (C): 22