Construction and Management Question on Estimation and Specification
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
A
6 months
B
6.5 months
C
7 months
D
7.5 months
Answer
6.5 months
Explanation
Solution
The correct answer is (B) : 6.5 months.