The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -

A

6 months

B

6.5 months

C

7 months

D

7.5 months

Answer

6.5 months

Explanation

Solution

The correct answer is (B) : 6.5 months.