Construction and Management Question on Estimation and Specification
The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
A
11.67 Months
B
10.67 Months
C
9.67 Months
D
8.67 Months
Answer
9.67 Months
Explanation
Solution
The correct answer is (C) : 9.67 Months.