The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -

A

11.67 Months

B

10.67 Months

C

9.67 Months

D

8.67 Months

Answer

9.67 Months

Explanation

Solution

The correct answer is (C) : 9.67 Months.