Construction and Management Question on Project management techniques e.g. PERT, CPM etc.
The network diagram of a construction project is shown in the following Figure. The duration of each activity, in days, and the early start time of the project are denoted in the diagram. The total project duration along the critical path, in days, is _____(in integer).
Answer
The correct answer is :18