The following figure shows the arrangement of formwork for casting a cantilever RC beam.
The correct sequence of removing the Shores/Props is:
A
S1↦S2↦S3↦S4↦S5
B
S5↦S4↦S3↦S2↦S1
C
S3↦S2↦S4↦S1↦S5
D
S3↦S4↦S2↦S5↦S1
Answer
S5↦S4↦S3↦S2↦S1
Explanation
Solution
The correct option is (2) :S5↦S4↦S3↦S2↦S1