Structural Engineering Question on Construction Management

The following figure shows the arrangement of formwork for casting a cantilever RC beam.
cantilever RC beam.
The correct sequence of removing the Shores/Props is:

A

S1S2S3S4S5S1 \mapsto S2 \mapsto S3 \mapsto S4 \mapsto S5

B

S5S4S3S2S1S5 \mapsto S4 \mapsto S3 \mapsto S2 \mapsto S1

C

S3S2S4S1S5S3 \mapsto S2 \mapsto S4 \mapsto S1 \mapsto S5

D

S3S4S2S5S1S3 \mapsto S4 \mapsto S2 \mapsto S5 \mapsto S1

Answer

S5S4S3S2S1S5 \mapsto S4 \mapsto S3 \mapsto S2 \mapsto S1

Explanation

Solution

The correct option is (2) :S5S4S3S2S1S5 \mapsto S4 \mapsto S3 \mapsto S2 \mapsto S1