Solveeit Logo

Question

Quantitative Ability and Data Interpretation Question on Time and Work

Stuart, Jack and Leo are colleagues working in a plant. Stuart and Jack can do a work in 10 days, Jack and Leo can do the same work in 15 days while Stuart and Leo can do it in 12 days. All of them started the work together. After two days, Leo was shifted to some other work. How many days will Stuart and Jack take to finish the rest of the work?

A

9

B

12

C

8

D

7.5

Answer

7.5

Explanation

Solution

The correct option is (D): 7.5