Water Resources Engineering Question on PERT

Slack time in PERT Analysis

A

Can never be greater than zero

B

Is always zero for critical activities

C

Can never be less than zero

D

Is minimum for critical events

Answer

Is minimum for critical events

Explanation

Solution

The correct option is(D): Is minimum for critical events