Question
Water Resources Engineering Question on PERT
Slack time in PERT Analysis
A
Can never be greater than zero
B
Is always zero for critical activities
C
Can never be less than zero
D
Is minimum for critical events
Answer
Is minimum for critical events
Explanation
Solution
The correct option is(D): Is minimum for critical events