Quantitative Aptitude Question on Clock and Calendar
Ram can finish the work alone in 10 days, while Shyam alone can do so in 20 days. They start a work on Sunday. Ram works on Sunday, Monday, Wednesday and Friday. Shyam works on Sunday, Tuesday, Thursday and Saturday. On which day of the week the work gets finished?
A
Monday
B
Tuesday
C
Wednesday
D
Thursday
Answer
Wednesday
Explanation
Solution
The correct answer is (C);Wednesday