Question
Quantitative Ability and Data Interpretation Question on Time and Work
Rajesh can check the quality of 1000 items in 5 hours and Rakesh can complete 75% of the same job in 3 hours. How much time is required for both of them to check 1300 items, if Rakesh stops checking after 2 hours ?
A
3 hours
B
4 hours
C
2 hours
D
1 hours
Answer
4 hours
Explanation
Solution
The Correct Option is (B):4 hours