Solveeit Logo

Question

Quantitative Aptitude Question on Time and Work

One day, Rahul started a work at 9 AM and Gautam joined him two hours later.They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is

A

12

B

11.5

C

12.5

D

10

Answer

10

Explanation

Solution

Let's denote the work rate of Rahul as RR work/hour and the work rate of Gautam as GG work/hour.

  1. When both started together at 9 AM:
    The total time they worked together was 8 hours (from 9 AM to 5 PM). They would have finished the work in 7.5 hours (30 minutes earlier). So, their combined work rate when they started together would be:
    Total Work=(R+G)×7.5Total \ Work = (R + G) \times 7.5

  2. On the day Rahul started at 9 AM and Gautam joined him 2 hours later:
    Rahul worked for 2 hours alone, and then they worked together for the next 6 hours (from 11 AM to 5 PM). This gives:
    Total Work=2R+6(R+G)Total \ Work = 2R + 6(R + G)

Since the total work done in both scenarios is the same, we can equate the two expressions:

2R+6(R+G)=7.5(R+G)2R + 6(R + G) = 7.5(R + G)

Expanding and simplifying:
2R+6R+6G=7.5R+7.5G2R + 6R + 6G = 7.5R + 7.5G
8R+6G=7.5R+7.5G8R + 6G = 7.5R + 7.5G
0.5R=1.5G0.5R = 1.5G
R=3GR = 3G

Now, let's use the combined work rate from the first scenario:
Total Work=(R+G)×7.5Total \ Work = (R + G) \times 7.5

Using the relationship R=3GR = 3G, we get:
Total Work=(3G+G)×7.5Total \ Work = (3G + G) \times 7.5
Total Work=4G×7.5Total \ Work = 4G \times 7.5
Total Work=30GTotal \ Work = 30G

Now, using this total work with Rahul's individual work rate for the time he worked alone:
2R=2(3G)=6G2R = 2(3G) = 6G

Subtracting this from the total work to get the work done by both together:
30G6G=24G30G - 6G = 24G

This means that both of them, working together for 6 hours, did 24G24G of the work:
6(R+G)=24G6(R + G) = 24G Using R=3GR = 3G:
6(4G)=24G6(4G) = 24G

The relationship holds true.

Now, to find the time Rahul would take to complete the entire work by himself:

Using R=3GR = 3G:
Total Work=30GTotal \ Work = 30G

If Rahul does the entire work:
Time for Rahul=Total WorkR=30G3G=10 hoursTime \ for \ Rahul = \frac{Total \ Work}{R} = \frac{30G}{3G} = 10 \ hours

Rahul would take 10 hours to complete the work by himself.