Question
Infrastructure Planning Question on Traffic survey methods, Traffic flow Analysis
Match the items in Group-I with their corresponding items in Group–IIGroup I | Group II |
---|---|
(P) Floating floor | (1) Overflow control |
(Q) Float valve | (2) Delay not affecting a project |
(R) Metal float | (3) Acoustical buffer |
(S) Free float | (4) Plastering equipment |
(5) Traffic flow control |
A
P-3, Q-2, R - 4, S - 1
B
P-5, Q-1, R-3, S-4
C
P-3, Q-1, R-4, S − 2
D
P-1, Q-2, R-5, S - 4
Answer
P-3, Q-1, R-4, S − 2
Explanation
Solution
The correct answer is (C): P to 3, Q to 1, R to 4, S − 2