Construction Materials and Management Question on PERT

In PERT technique, the time estimate of activities and probability of their concurrence follows :

A

Normal distribution curve

B

β-distribution curve

C

Poisson distribution curve

D

Binomial distribution curve

Answer

β-distribution curve

Explanation

Solution

The correct answer is (B) : β-distribution curve.