Question
Construction Materials and Management Question on PERT
In PERT technique, the time estimate of activities and probability of their concurrence follows :
A
Normal distribution curve
B
β-distribution curve
C
Poisson distribution curve
D
Binomial distribution curve
Answer
β-distribution curve
Explanation
Solution
The correct answer is (B) : β-distribution curve.