In PERT Analysis, the time estimates of activities and probability of their occurence follow

A

Normal distribution curve

B

P- distribution curve

C

Possion's distribution curve

D

Bionomial distribution curve

Answer

P- distribution curve

Explanation

Solution

The correct option is(B): P- distribution curve