In order to ensure that no scouring take place in the bed of a channel of bed slope 'S' constructed on alluvial soil of particle size 'd' cm, the flow velocity should be restricted.
A
4.85d21s−61
B
4.85d21s61
C
0.48d21s−61
D
0.48d21s61
Answer
4.85d21s−61
Explanation
Solution
The correct option is(A): 4.85d21s−61