Solveeit Logo

Question

Quantitative Aptitude Question on Time and Work

If P, Q and R work together, they take 12 days to complete the work. However, if only P and R work, they take 20 days to complete the work. A schedule is made such that P and R work every day, while Q joins them only on alternate days i.e. on 1st, 3rd, 5th, 7th,… days. On which day will the work be completed?

A

15th

B

14th

C

13th

D

17th

Answer

15th

Explanation

Solution

The correct answer is (A),15th