Question: If in \(5\) days, working \(2\) hours a day, \(10\) people can do a piece of work, then how long wil...

If in 55 days, working 22 hours a day, 1010 people can do a piece of work, then how long will 22 people take to do the same work, working 55 hours a day?
A. 55 days
B. 88 days
C. 1010 days
D. 1212 days
D. None of these

Explanation

Solution

This given question is related to the concept of mensuration. The sub-topic of menstruation is time and work. We will try to find how much of the total work is to be done. To find the total work unit, we use the formula:

Work unit = Number of men doing the work ×\times Number of hours ×\times Number of days , then find the number of days.

Complete step by step solution:
We are given that 1010 people working 22 hours per day can do a piece of work in 55 days.
The total work done is =10×2×5=100 = 10 \times 2 \times 5 = 100
We can conclude that 1010 people working at 22 hours per day can do 100100 units of work in 55 days.
Therefore, the number of days required by 22 people, working at 55 hours per day =1002×5=10 = \dfrac{{100}}{{2 \times 5}} = 10
So, 22 people working at 55 hours per day can do the same piece of work in 1010 days.

So, the correct answer is Option (C).

Note: The given question was an easy one. Whenever such types of questions appear then, first try to find out the total amount of work units, here 1010 people working at 22 hours per day could do the work in 55 days, so using this information we could easily find out the amount of work done. Students can practice similar questions for more clarity and better understanding.