Question
Business Studies Question on Project Planning
Identify the correct sequence of steps under the Planning function:
(A) Setting objectives
(B) Identifying alternative courses of action
(C) Developing premises
(D) Evaluating alternative courses of action
A
(A), (B), (C), (D)
B
(A), (C), (B), (D)
C
(B), (A), (D), (C)
D
(C), (B), (D), (A)
Answer
(A), (C), (B), (D)
Explanation
Solution
The correct sequence in planning is: Setting objectives, Developing premises, Identifying alternative courses of action, Evaluating alternative courses of action.