Construction Materials and Management Question on PERT
Given below are two statements:
Statement - I: PERT is most suitable for research and development type of projects as it account for uncertainties involved in estimation of time estimates.
Statement - II: Acritical path, method is suitable for repetitive type of projects for example construction projects.
In the light of the above statements, choose the correct answer from the options given below :
A
Both Statement I and Statement II are true.
B
Both Statement I and Statement II are false.
C
Statement I is true but Statement II is false.
D
Statement I is false but Statement II is true.
Answer
Both Statement I and Statement II are true.
Explanation
Solution
The correct answer is (A) : Both Statement I and Statement II are true..