Solveeit Logo

Question

Quantitative Aptitude Question on Time and Work

Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is

A

30

B

36

C

70

D

None of Above

Answer

36

Explanation

Solution

Let's assume W be the total amount of work.
And g and s be the efficiencies of Gautam and Suhani respectively.
According to the question:
g + s = W20\frac{W}{20} (1 day work) ….. (i)

And given that Gautam is doing only 60%: 3g5\frac{3g}{5}
Suhani is doing 150%: 3s2\frac{3s}{2}
Now, using this, we get:

3g5+3s2=W20\frac{3g}{5}+\frac{3s}{2}=\frac{W}{20} (1 day work)

g + s = 3g5+3s2\frac{3g}{5}+\frac{3s}{2}

sg=45\frac{s}{g}=\frac{4}{5}
This implies that Gautam is more efficient person.
By using equation (i) , we get :
g+4g5=W20g+\frac{4g}{5}=\frac{W}{20}

95g=W20\frac{9}{5}g=\frac{W}{20}

g=W36g=\frac{W}{36}
Therefore, Gautam takes 36 days to finish the given work.
So, the correct option is (B) :36.