Question
Quantitative Aptitude Question on Time and Work
Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is
30
36
70
None of Above
36
Solution
Let's assume W be the total amount of work.
And g and s be the efficiencies of Gautam and Suhani respectively.
According to the question:
⇒ g + s = 20W (1 day work) ….. (i)
And given that Gautam is doing only 60%: 53g
Suhani is doing 150%: 23s
Now, using this, we get:
⇒ 53g+23s=20W (1 day work)
⇒g + s = 53g+23s
⇒ gs=54
This implies that Gautam is more efficient person.
By using equation (i) , we get :
⇒ g+54g=20W
⇒ 59g=20W
⇒ g=36W
Therefore, Gautam takes 36 days to finish the given work.
So, the correct option is (B) :36.