Question
General Knowledge Question on General Knowledge Based
For a given activity, the optimistic time, pessimistic time and most probable estimates are 5, 17, 8 days respectively. The expected time is
A
8 days
B
9 days
C
10 days
D
15 days
Answer
9 days
Explanation
Solution
The correct option is(B): 9 days