For a given activity, the optimistic time, pessimistic time and most probable estimates are 5, 17, 8 days respectively. The expected time is

A

8 days

B

9 days

C

10 days

D

15 days

Answer

9 days

Explanation

Solution

The correct option is(B): 9 days