Operations Research and Operations Management Question on Project Management

Five jobs A, B, C, D and E are available at time t = 0 for processing at a machine, and their processing times are listed.JobABCDE
Processing time (in days)96458
If the jobs are processed using the shortest processing time (SPT) rule, the average flow time (in days) is _____ . (Rounded off to 1 decimal place)
Answer

The answer is 16.6