Question
Operations Research and Operations Management Question on Project Management
Five jobs A, B, C, D and E are available at time t = 0 for processing at a machine, and their processing times are listed.Job | A | B | C | D | E |
---|---|---|---|---|---|
Processing time (in days) | 9 | 6 | 4 | 5 | 8 |
If the jobs are processed using the shortest processing time (SPT) rule, the average flow time (in days) is _____ . (Rounded off to 1 decimal place) |
Answer
The answer is 16.6