Structural Engineering Question on Construction Management

Consider the statements P and Q.
P : In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q : A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT ?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

Answer

Both P and Q are TRUE

Explanation

Solution

The correct option is (A) : Both P and Q are TRUE.