Consider the statements P and Q.
P : In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q : A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT ?
A
Both P and Q are TRUE
B
P is TRUE and Q is FALSE
C
Both P and Q are FALSE
D
P is FALSE and Q is TRUE
Answer
Both P and Q are TRUE
Explanation
Solution
The correct option is (A) : Both P and Q are TRUE.