Structural Engineering Question on Construction Management

Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The 'schedule variance' for the project is

A

(-)Rs. 50

B

(-)50 days

C

(+)Rs. 50

D

(+)50 days

Answer

(-)Rs. 50

Explanation

Solution

The correct option is (A) : (-)Rs. 50.