Geomatics Engineering Question on Principles of surveying

At a fixed instrument location in levelling, if the backsight reading at a point P is more than the foresight reading at a point Q, then

A

point P has lower elevation than point Q

B

point P has higher elevation than point Q

C

the elevation difference between P and Q depends on height of the instrument

D

the elevation difference between P and Q depends on benchmark elevation

Answer

point P has lower elevation than point Q

Explanation

Solution

The correct answer is (A) : point P has lower elevation than point Q