An overhead water tank of 7200 m3 capacity is being filled with water. The delivery of the pump filling the tank is 5/6th of the delivery of the pump discharging the same tank. As a result, 24 minutes more is needed to fill the tank than discharge it. Determine the delivery of the pump in filling the tank.

A

90 m3/min

B

72 m3/min

C

60 m3/min

D

50 m3/min

Answer

50 m3/min

Explanation

Solution

Let the delivery of the pump filling the tank = X m3/min
⇒ delivery of the pump discharging the tank = 65\frac{6}{5}X m3/min
7200X720065X=24\frac{7200}{X}-\frac{7200}{\frac{6}{5}X}=24
1200X=24\frac{1200}{X}=24
⇒ X=50.
So, the correct option is (D): 50 m3/min