Solveeit Logo

Question

Textile Engineering and Fibre Science Question on Yarn Manufacture, Structure and Properties

A winder operates at 750 m/min with 93% efficiency. The time (in minutes) taken for the winder to wind 1.2 kg of 20 tex yarn is approximately _______.

A

68

B

74

C

86

D

90

Answer

86

Explanation

Solution

The correct option is (C):86