Question
Quantitative Aptitude Question on Time and Work
‘A’ while working 40% more efficiently can complete a piece of work in 25 days and ‘B’ while working 25% more efficiently can complete the same work in 21 days. While working with their original efficiencies ‘A’ and ‘B’ together worked for 9 days, then find the time taken by ‘A’ alone to complete the remaining work with his original efficiency.
7 days
14 days
12 days
6 days
14 days
Solution
Let total amount of work be 525 units
Amount of work done by ‘A’ in one day (with increased efficiency) = 25525 = 21 units
Original efficiency of ‘A’ = 1.4021 = 15 units per day
Amount of work done by ‘B’ in one day (with increased efficiency) = 21525 = 25 units
Original efficiency of ‘B’ = 1.2525 = 20 units per day
Amount of work completed by ‘A’ and ‘B’ together in 9 days = 35 × 9 = 315 units
Remaining work = 525 – 315 = 210 units
Desired time = 15210 = 14 days
So, the correct option is (B) : 14 days.