Mathematics Question on Quadratic Equation
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, then the time taken by B to finish the work is
A
12 days
B
14 days
C
16 days
D
18 days
Answer
12 days
Explanation
Solution
The correct option is (A): 12 days