Question: A started work and left after working for 2 days. Then B was called and he finished the work in 9 da...

A started work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them working alone to finish the whole work?
A. 5 days, 8.5 days
B. 2.5 days, 7.5 days
C. 5 days. 15 days
D. 3 days, 15 days

Explanation

Solution

In the above question, first of all, we will suppose A and B can do the work in x and y days. Then, we will find the work done by A or B in the given days by using the simply unitary method and write the sum of work that is equal to 1.

Complete step-by-step answer:

We have been given that, A started a work and left after working for 2 days and the remaining work is completed by B in 9 days. Also, if A left the work after working for 3 days, B would have finished the remaining work in 6 days.
Let us suppose, A and B can do the work in x and y days respectively.
Now, we know that the sum of work done by A and B is equal to 1.
In x days work done by = 1\text{A }=\text{ 1}
In 1 day work done by =1x\text{A }=\dfrac{1}{x}
So, in 2 day work done by =2x\text{A }=\dfrac{2}{x}
Similarly, in 3 day work done by =3x\text{A }=\dfrac{3}{x}
Again, In y days work done by = 1\text{B }=\text{ 1}
In 1 day work done by =1y\text{B }=\dfrac{1}{y}
So, in 9 days work done by =9y\text{B }=\dfrac{9}{y}
Similarly, in 6 days work done by =6y\text{B }=\dfrac{6}{y}
According to question, we have,

& \dfrac{2}{x}+\dfrac{9}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (i)} \\\ & \dfrac{3}{x}+\dfrac{6}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (ii)} \\\ \end{aligned}$$ Let us suppose, $$\dfrac{1}{x}=a\text{ and }\dfrac{1}{y}=b,$$ then, the equations become, $$\begin{aligned} & 2a+9b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iii)} \\\ & 3a+6b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iv)} \\\ \end{aligned}$$ On performing $$(iv)\times 2-(iii)\times 3,$$ we get, $$\begin{aligned} & \left( 6a+12b \right)-\left( 6a+27b \right)=2-3 \\\ & 6a+12b-6a-27b=-1 \\\ \end{aligned}$$ On cancelling similar terms, we get, $$\begin{aligned} & -15b=-1 \\\ & b=\dfrac{1}{15} \\\ \end{aligned}$$ Since, $$b=\dfrac{1}{y}$$ $$\begin{aligned} & \dfrac{1}{y}=\dfrac{1}{15} \\\ & y=15\text{ }days \\\ \end{aligned}$$ On substituting $$b=\dfrac{1}{15}$$ in equation (iii), we get, $$\begin{aligned} & \Rightarrow 2a+9\times \dfrac{1}{15}=1 \\\ & \Rightarrow 2a+\dfrac{3}{5}=1 \\\ & \Rightarrow 2a=1-\dfrac{3}{5} \\\ & \Rightarrow 2a=\dfrac{5-3}{5} \\\ & \Rightarrow 2a=\dfrac{2}{5} \\\ & \Rightarrow a=\dfrac{1}{5} \\\ \end{aligned}$$ Since, $$a=\dfrac{1}{x}$$ $$\begin{aligned} & \dfrac{1}{x}=\dfrac{1}{3} \\\ & x=5\text{ days} \\\ \end{aligned}$$ Therefore, A and B finish the work in 5 days and 15 days respectively. So, the correct option is C. **Note:** While solving the equation $$\dfrac{1}{x}\text{ and }\dfrac{1}{y}$$ it is better to take $$\dfrac{1}{x}\text{=a and }\dfrac{1}{y}=b$$. Otherwise, it is very difficult to solve the equation also, it will take you a lot of time. Also, remember that after solving the equation in a and b you have to further substitute the value of a and b in terms of x and y, which will give us the final answer.