Question
Question: A started work and left after working for 2 days. Then B was called and he finished the work in 9 da...
A started work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them working alone to finish the whole work?
A. 5 days, 8.5 days
B. 2.5 days, 7.5 days
C. 5 days. 15 days
D. 3 days, 15 days
Solution
In the above question, first of all, we will suppose A and B can do the work in x and y days. Then, we will find the work done by A or B in the given days by using the simply unitary method and write the sum of work that is equal to 1.
Complete step-by-step answer:
We have been given that, A started a work and left after working for 2 days and the remaining work is completed by B in 9 days. Also, if A left the work after working for 3 days, B would have finished the remaining work in 6 days.
Let us suppose, A and B can do the work in x and y days respectively.
Now, we know that the sum of work done by A and B is equal to 1.
In x days work done by A = 1
In 1 day work done by A =x1
So, in 2 day work done by A =x2
Similarly, in 3 day work done by A =x3
Again, In y days work done by B = 1
In 1 day work done by B =y1
So, in 9 days work done by B =y9
Similarly, in 6 days work done by B =y6
According to question, we have,