Quantitative Aptitude Question on Time and Work
A started a work and left after working for 1 day. Then B was called and he finished the work in 421 days. Had A left the work after working for 121days, B would have finished the remaining work in 3 days. In how many days can each of them, working alone, finish the whole work?
A
3.5 days, 8.5 days
B
2.5 days, 7.5 days
C
5 days, 15 days
D
None of these
Answer
2.5 days, 7.5 days
Explanation
Solution
The correct option is (B): 2.5 days, 7.5 days