A project network with the sequence of five activities is shown.
A project network with the sequence of five activities

The crashing costs of activities areActivityABCDE
Duration (week)56834
Crashing cost per week (lakh INR)4.02.52.03.04.0
If the project is crashed by one week, the increase in project cost, in lakh INR, is
A

2.0

B

2.5

C

3.0

D

4.0

Answer

2.5

Explanation

Solution

The correct option is (B): 2.5