Question
Systems Engineering Question on Network Analysis
A project network with the sequence of five activities is shown.
The crashing costs of activities areActivity | A | B | C | D | E |
---|---|---|---|---|---|
Duration (week) | 5 | 6 | 8 | 3 | 4 |
Crashing cost per week (lakh INR) | 4.0 | 2.5 | 2.0 | 3.0 | 4.0 |
If the project is crashed by one week, the increase in project cost, in lakh INR, is |
A
2.0
B
2.5
C
3.0
D
4.0
Answer
2.5
Explanation
Solution
The correct option is (B): 2.5