A project has six activities and the precedence relationship among them is shown in the table.Activity | Precedent activities |
---|---|
A | None |
B | None |
C | None |
D | A, B |
E | B,C |
F | A, B |
The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is ___ . |
A
0
B
1
C
2
D
3
Answer
3
Explanation
Solution
The correct option is (D): 3.