Question
Quantitative Ability and Data Interpretation Question on Time and Work
A is able to do a piece of work in 10 days and B can do the same work in 15 days. If they can work together for four days, what is the fraction of work left?
A
21
B
32
C
23
D
31
Answer
31
Explanation
Solution
Let's solve the problem step by step.
A can do the work in 10 days, so A's work rate is:
101 of the work per day
B can do the work in 15 days, so B's work rate is:
151 of the work per day
Working together, A and B's combined work rate is:
101+151=303+302=305=61 of the work per day
In 4 days, A and B together can complete:
4×61=64=32 of the work
The fraction of the work left is:
1−32=31
Therefore, the fraction of work left is:
Answer: D (31)