Question
Quantitative Aptitude Question on Time and Work
A group of N people worked on a project.They finished 35% of the project by working 7 hours a day for 10 days.Thereafter,10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day.Then the value of N is
23
140
36
150
140
Solution
The correct answer is B:140
In the first phase,the group finished 35% of the project by working 7 hours a day for 10 days.
In the second phase,after 10 people left, the remaining people finished the rest of the project in 14 days by working 10 hours a day.
Let's denote the total work required for the project as W.
In the first phase:
Work done=0.35×W
Work rate=(Numberofpeople)×(Hoursperday)×(Days)=N×7×10
In the second phase:
Work done=0.65×W(since100%−35%=65%remains)
Work rate=(Remainingnumberofpeople)×10×14=(N−10)×10×14
Since work done equals work rate in each phase, we can set up the following equations:
0.35×W=N×7×10
0.65×W=(N−10)×10×14
Now we can solve for N:
From equation 1: W=0.35(N×7×10)
From equation 2: W=0.65((N−10)×10×14)
Since both expressions are equal to W, we can set them equal to each other:
0.35(N×7×10)=0.65((N−10)×10×14)
Now solve for N:
(N×7×10×0.65)=((N−10)×10×14×0.35)
Simplify:
7×10×0.65×N=10×14×0.35×(N−10)
Now solve for N:
4.55×N=4.9×(N−10)
Distribute on the right side:
4.55×N=4.9×(N−49)
Subtract 4.55×N from both sides:
0.35×N=49
Now solve for N:
N=0.3549
N=140
So,the initial number of people in the group (N) is 140.