Question
Quantitative Aptitude Question on Time and Work
A factory produces a certain number of toys in a week using a team of 40 workers who work for 8 hours daily. Due to an increase in demand, the factory needs to double the production while maintaining the same work schedule. How many additional workers should be hired?
44
40
38
36
40
Solution
The total work done is directly proportional to the number of workers and the number of hours they work.
For the current situation:
Total work done = 40 workers × 8 hours/day × 7 days/week = 2240 worker-hours/week
To double the production, the total work done should be doubled:
New total work done = 2 × 2240 worker-hours/week = 4480 worker-hours/week
With the new team of (40 + W) workers working 8 hours daily for 7 days:
New total work done = (40 + W) workers × 8 hours/day × 7 days/week
Equating the two expressions for new total work done:
(40 + W) × 8 × 7 = 4480
40 + W = 80
W = 40