Mathematics Question on Time and Work

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days 47\frac{4}{7} of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

A

80

B

81

C

82

D

83

Answer

81

Explanation

Solution

The correct option is (B); Formula = M1D1H1W1\frac{ M_{1} D_{1}H_{1}}{ W_{1} }=M2D2H2W2\frac{ M_{2} D_{2}H_{2}}{ W_{2} }
117 men completed 47\frac{4}{7} work in 33 days working 8 hours per day.
Let xx men complete the remaining 37\frac{3}{7} work in 13 days working 9 hours per day.
177×33×84\frac{177\times33\times8}{4}=x×13×93 \frac{x\times13\times9}{3}
x=33×2×3x = 33\times2\times3 = 198
\therefore Additional mens are 198-117 = 81