Mathematics Question on Time and Work

A completes 720\frac{7}{20} of a work in 10 days. Then he completes the remaining work with the help of B in 5 days. The time required for A and B together to complete the entire work is :

A

10029\frac {100}{29} days

B

10013\frac {100}{13} days

C

10017\frac {100}{17} days

D

20013\frac {200}{13} days

Answer

10013\frac {100}{13} days

Explanation

Solution

The correct option is (B):10013\frac {100}{13} days