A certain number of people were supposed to complete a work in 24 days. The work, however, took 32 days, since 9 people were absent throughout. How many people were supposed to be working originally?

A

32

B

27

C

36

D

30

Answer

36

Explanation

Solution

Using M1D1= M2D2
Let xx people were supposed to work initially.
x×24=(x9)×32x×24 =(x−9)×32
3x=4(x9)3x =4(x−9)
3x=4x363x =4x−36
x=36x=36