Question
Quantitative Aptitude Question on Time and Work
A certain number of men can complete a piece of work in 60 days. If there were 8 more men, the work could be finished in 10 days less. How many men were there originally?
A
40
B
50
C
80
D
100
E
110
Answer
40
Explanation
Solution
The correct option is (A): 40.