Solveeit Logo

Question

Question: \(A\) can do \(\dfrac{2}{3}\) of a certain work in \(16\) days and \(B\) can do \(\dfrac{1}{4}\) of ...

AA can do 23\dfrac{2}{3} of a certain work in 1616 days and BB can do 14\dfrac{1}{4} of the same work in 33 days. In how many days can both finish the work, working together?

Explanation

Solution

Since they are individually doing the same work, we can find their capacities. We need to find the work done by them in a single day. Then we can calculate the number of days needed to finish the work.

Formula used: If xx is the number of days and w is the work done per day, then total work done is wxwx.

Complete step-by-step answer:
Given that AA can complete 23\dfrac{2}{3}of the given work in 1616 days.
So AA can complete the total work (that is 33=1\dfrac{3}{3} = 1 of the work) in 16×32=2416 \times \dfrac{3}{2} = 24 days.
Also given BB can complete 14\dfrac{1}{4} of the same work in 33 days.
So BB can complete the total work in 3×4=123 \times 4 = 12days.
Therefore, the work done by A,BA,B in a single day is 124,112\dfrac{1}{{24}},\dfrac{1}{{12}} respectively.
wA=124,wB=112\Rightarrow {w_A} = \dfrac{1}{{24}},{w_B} = \dfrac{1}{{12}}
So the total work done by them in a single day is w=wA+wB=124+112=124+224=324=18w = {w_A} + {w_B} = \dfrac{1}{{24}} + \dfrac{1}{{12}} = \dfrac{1}{{24}} + \dfrac{2}{{24}} = \dfrac{3}{{24}} = \dfrac{1}{8}
Let they take xx days to complete the whole work, working together.
We have to find xx.
If xx is the number of days and ww is the work done per day, then total work done is wxwx.
Here, w=18w = \dfrac{1}{8} and total work can be considered as 11.
18x=1\Rightarrow \dfrac{1}{8}x = 1
x=1×8=8\Rightarrow x = 1 \times 8 = 8
So AA and BB need 88 days to finish the work, working together.

Note: The point should be noted is that work done is proportional to the time taken. The more is the time, the more is the work. But the more is the number of workers, the less is the time taken.