Mathematics Question on Time Speed and Distance

A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work?

A

4.33

B

4

C

4.66

D

5.33

Answer

4

Explanation

Solution

The correct option is (B): 4