A can do a job in 9.8 days and B can do it in 14 days. They work together for 3.5 days, and A goes away. In how many days will B finish the remaining work?

A

3.6 days

B

5.5 days

C

6.3 days

D

7.2 days

Answer

5.5 days

Explanation

Solution

The correct answer is (B);5.5 days