Quantitative Aptitude Question on Time and Work
A can do a job in 9.8 days and B can do it in 14 days. They work together for 3.5 days, and A goes away. In how many days will B finish the remaining work?
A
3.6 days
B
5.5 days
C
6.3 days
D
7.2 days
Answer
5.5 days
Explanation
Solution
The correct answer is (B);5.5 days