A can do a job in 24 days and B can do the same job in 26 days. A and B do the work in alterative days. If 'B' starts the work, find in how many days the job got complete

A

25

B

27

C

24

D

35

E

None of these

Answer

None of these

Explanation

Solution

The correct option is (E): None of these.