Question
Quantitative Aptitude Question on Time and Work
A can complete a task in 6 days, B can complete it in 8 days, and C can complete it in 12 days. If they all work together, how many days will be required to complete the task?
A
5 days approx
B
2 days approx
C
4 days approx
D
3 days approx
Answer
3 days approx
Explanation
Solution
The correct option is (D): 3 days approx